Updated 4 October 2024. Next update: Friday 8 November 2024.
The current situation
Work has continued to progress well at Rothesay and the overall projects is now around 70% complete.
Our diving team is currently working beneath the linkspan to construct the final section of wall in that area. They will soon move over to the current overnight berth area to construct the final section of wall. When this begins, the ferry will move to the front berth nearer the building to allow the divers access.
The team has worked as quickly as they can and made good use of the recent calm weather conditions. As we move into autumn and winter there is potential for disruption to the work especially if weather conditions are particularly windy or wave swell is increased. Safety of the dive team is our most important consideration and we will continue to add updates to this page as the work draws to a close.
Diagram shows progress of work up to October 2024. Concrete consolidation shown in green - complete. First area of toe wall construction shown in orange - complete. Second area of toe wall construction shown in yellow - in progress.
Previous work
The contractor started work, on site, on 27 May as planned and compounds have been set up on the main Rothesay Harbour pier and the Albert Pier, which will receive material deliveries. Plant and equipment, including a crane and barge, have been delivered to the site.
Rock armour consolidation is now 100% complete, and the dive inspections to check this work are also complete.
The overall project is now around 45% complete, a fantastic effort from our Contractor and Supervision teams.
Work has now started to build the toe wall at the foot of the original harbour wall. The purpose of this is to prevent any further loss of seabed material from around the base of the original wall and protect the wall against wave and wash from vessels using the harbour.
The first section of toe wall is between to the two areas of rock armour that have been consolidated. Work involves digging a trench to place bolster bags in. These bags are then filled with concrete and tie together using reinforcing bars. The wall is built in steps, allowing each layer of concrete to harden before the next layer is placed.
The skilled construction divers have to move carefully when filling the bolster bags and be careful not to tear them. A difficult job whilst working beneath the water.
Background
Works at Rothesay Harbour will support the future of the pier by preparing it to accommodate larger, more powerful vessels than the original pier was built to withstand.
PվɫÇéƬ has appointed Shearwater Marine Ltd to undertake £1.9m stabilisation works at Rothesay Harbour. Maintaining ports and harbours is just one of the services our council provides that others don’t need to.
The contractor will mobilise at the harbour during the week beginning 20 May and the first dive is scheduled to take place on Monday 27 May
Shearwater Marine Ltd will carry out work overnight to minimise disruption to ferry operations and day-to-day travel for Bute residents and visitors should be mainly unaffected.
However, to allow the contractor access to the site, the berth will not be available overnight. This will mean one of the Bute ferries will berth overnight in Gourock.
Work should take nine months to complete, and this is dependent on the weather and supply of materials.
Stabilisation works at the harbour include:
- Constructing a toe (retaining) wall at the base of the original wall to provide stability to the main harbour structure. This will extend 143m from the eastern edge of the harbour wall to the overnight ferry berth
- The toe wall will prevent any potential sliding or further loss of fine materials from the sea bed behind the original wall.
- Repair to the surface of the harbour where there has been visible settlement.
This new work builds on previous investment at the harbour to minimise scour, and so mitigate damage done by vessels over the years. Scour is when the seabed is dug out by vessels moving the water and creating channels against the harbour wall. We fitted a wavescreen which prevents vessels moving the water and creating scour and so protects the harbour wall. Since the wavescreen was fitted, we have seen a notable reduction of settlement on the top of the harbour wall.
For information on revised ferry timetables visit the .